Capital Works Update

November 12, 2021

It was great to see works recommence on the Junior Campus courts after a short delay. This week new turf has been laid out. What a difference this has made already. In the coming days, the new basketball/netball rings will be installed and lines marked. Following the completion of this work, the existing fence will be taken down, posts painted and new wire, together with a new section of gates, will be installed to complete the project.

While this work has been occurring, the renovations in the Junior Campus Art room have also started. Some of the existing cupboards and the old sink have been removed, as well as the demolition of the fixed cupboards in the adjoining store room. The next couple of weeks will see walls patched and painted and a new sink installed in preparation for new carpet and lino by the end of the year.